Decisions:
- The tool should be executed through the AquaNES DSS. This would be just a selection button that executes the link to the tool. Within the tool there should also be a link back to the DSS.
- The R based tool of KWB will be used as the back-end calculator. Patrick, Wolfgang and Michael will be in contact on further changes of settings / improvements *(peer to peer discussion) (summer 2018),
- The platform containing data, tools and front end can (in principle) also run other tools. This is not foreseen within aquaNES
Actions:
Generic
-
Thomas checks available microbial data in different sites (esp. site 8)for progress check Check available microbial data in different sites (esp. site 8) #9 -
Thomas will organize a conference call in the week before July 21st, in order to align activities on the data terminology and (additional) parameter requirements between Patrick, Michael, Ulf and Mark – Ulf will fix the agendafor minutes see Telefone conferene (2018-07-05) wrap-up #10 -
Ulf selects Greek site for QMRAfor progress check Select Greek site for testing of QMRA tool #11
Data
-
Define uniform naming and units for parameters and system settings and characteristics: Wastewater treatment + AquaNES demonstrated technologies (Michael KWB), Drinking water treatment (Patrick KWR) Deadline july 21st, for progress check Define uniform naming and units for parameters and system settings and characteristics #1 -
Develop initial (default value) dataset in order to enable to run the system (Michael KWB) (July?? 2018), for progress check Develop initial (default value) dataset in order to enable to run the system #2 -
Compile database with available data from KWR-KWB, AquaNES other sources for more comprehensive and interactive QMRA and apply uniform structure on naming (KWB, KWR) (filling until the end of project), for progress check Compile database with available data #3
Back-end / engine
-
R-tool potentially adapted after peer to peer discussions and QMRA spot comparison (Wolfgang/Michael KWB, Patrick KWR), (deadline November?), for progress check Test/QA of back-end (R package kwb.qmra) #4
Web based interface / front end
-
Feed back from Budapest WW on front end design (storyboard) in conference call or similar (Mark, (Alifta), Anthony (Patrick) ; contacts through Thomas KWR) (deadline july)for progress check Feedback on frontend design (storyboard) #6 -
Adapt tool with feedback Budapest WW (Mark, (Alifta), Anthony??) (deadline sept 2018)for progress check Adapt frontend (storyboard) with feedback Budapest WW #7 -
Test dummy run of beta version by Budapest water under supervision of QMRA team (people to be appointed) deadline nov 2018 >> suggestion in long breakout session in Athens m 30 meeting on site instead of via internet, include also other partners from workpackage 1, 2, 3?!for progress check Test dummy run of beta version by Budapest water #8
Source: email from Thomas (received: 2018-06-08 10:03, updated after telefone conference on 2018-07-5 20:30)